Middle School Project - March Update

This update includes:
- Neighborhood & Abutter Meeting
- Project Update to the Board of Education
- Building Committee – March Meeting Notes
- Resources
- Sign Up for Email Notifications
-------------------------------------------------
Neighborhood & Abutter Meeting
The Concord School District will hold a meeting on Thursday, March 12 at Rundlett Middle School to discuss the middle school construction project.
The project team will share a construction timeline and its impact on the school and the surrounding neighborhoods, as well as an overview of the traffic impact. A full presentation of the traffic report is available on the district’s YouTube channel: Building Committee Meeting - February 5, 2026.
Date: Thursday, March 12, 2026 at 6:00-7:00pm
Location: Rundlett Middle School – New Activity Room
The meeting will be recorded by Concord Community Television and posted online the next day.
Matt Cashman
Owners’ Project Manager
Director of Facilities & Planning
Project Update to the Board of Education
District administration created a report which will be shared with the Board of Education each month.
|
Building size: projected: 205,562 sf Mechanical enclosures: 8,933 sf (additional) Enrollment capacity: 900 Total project approved budget $155,718,801 |
Location: 146 South Street Construction start: April 2026 School opens: December 2028 Project status: On Schedule |
February 2026 – Project Milestones
|
Project Milestone |
Date |
|---|---|
|
Naming the Middle School
|
February 4 Suggest a Name for the Middle School |
|
Building Committee Meeting
|
February 5 |
|
State Fire Marshall Review
|
February 11 |
|
Board of Education
|
February 19 |
|
Athletics Planning
|
February 20 |
Upcoming Milestones
|
Upcoming Milestone |
Date |
|---|---|
|
Meeting with local building code enforcement officer |
March 3 |
|
Sustainability Committee Meeting |
March 3 |
|
Building Committee Meeting |
March 5 |
|
Naming the Middle School – last day to submit names |
March 20 |
|
Meeting with abutters |
March 12 |
|
60% Construction documents & early bid package |
April 1 |
|
Groundbreaking Ceremony |
TBD |
Financials
|
Item |
$$ |
|
Total project budget |
$168,777,480 |
|
Estimated tax credits & rebates |
$(8,378,745) |
|
Other credits – early bid package |
$(2,119,520) |
|
Subtotal tax credits, rebates, other credits |
$(13,058,679) |
|
Net Projected Cost Budget |
$155,718,801 |
Note – Once the project starts, future reports will include costs incurred to date and additional financials details
Project Team
- Architect: HMFH Architects
- Construction Manager: Harvey Construction
- Concord School District
- Pamela Walsh – President, Board of Education/Chair, Building Committee
- Elizabeth Boucher – Chair, Capital Facilities Committee
- Timothy Herbert – Superintendent
- Matt Cashman – Owner's Project Manager
- Jack Dunn – Business Administrator
- Jay Richard – Principal, Rundlett Middle School
- Terry Wolf – Director of Communication
-------------------------------------------------
Building Committee Meeting Notes – March 5, 2025 (Meeting Video)
Agenda
- LEED Certification
- Exterior
Discussion Highlights
- LEED Certification - the committee recommended to Board that the district "purse LEED certification towards the goal of gold in the two-step review process"
- Exterior - HMFH reviewed examples of brick and patterns for the exterior of the building
-------------------------------------------------
Resources
Middle School Project webpage: Middle School Project. This page includes several years of presentations and documents.
Sign Up for Email Notifications
Updates are sent via the district’s ParentSquare app. Share this with anyone that would be interested: Join Community Groups and select “Middle School Project.” No phone number is necessary.