December 15, 2025
Middle School Project Update - December 2025

This update includes:
- Key Dates
- Building Committee – December Meeting Summary
- Resources
- Sign Up for Email Notifications
Key Dates
- December 17 – Submit plans to the Planning Board
- January 5 – Board of Education – Public Hearing for Bond Resolution
- January 6 - Architectural Design Review Commission
- January 8 – Building Committee meeting
- January 15 – Submit Alteration of Terrain permit
- January 21 - Planning Board Review
- April 1 - 60% Construction Documents & Early Bid Package
- May 1 - 60% Cost Estimate
- August – 100% Construction Documents
Building Committee Meeting Notes – December 4, 2025
Agenda – HMFH Presentation
- PV Procurement Update
- Main Street Design Development
- Media Center Design
- Career Pathway Spaces (Food Tech, Wood Shop, Robotics)
- Budget & Schedule Updates
- Traffic & Pedestrian Access
- Other
Discussion Highlights
- PV Procurement
- Moving forward with solar panel procurement to be eligible for ITC tax credit
- Safe harbor requires purchasing 5–10% of panels by Dec 31
- Goal: Maximize rooftop installation; minimize canopy
- Estimated tax credit: ~30% of $5M budget (~$1.5M)
- Main Street Design
- Cafeteria centrally located; defined with low walls and benches
- Ramp designed for accessibility and multiple gathering zones
- Acoustic concerns addressed with soft surfaces and rated partitions
- Storage planned under ramp and in adjacent rooms
- Media Center
- Located on second floor above entry; accommodates two classes
- Includes maker space, recording studio, tech help desk
- Daylighting studies underway; shades planned for glare control
- Career Pathway Spaces
- Food Tech Classroom: Fully independent kitchen, flexible for events and programs
- Wood Shop: Flexible layout, outdoor access, dust collection under review
- Robotics Classroom: Adjustable tables, computer stations, storage solutions
- Budget & Schedule
- Next cost estimate at 60% design due April 1
- Final drawings by August
- Loan resolution hearing scheduled for January 5; financing options under review
- Geothermal test well completed; report expected by year-end
- Traffic & Pedestrian Access
- Transportation engineer engaged; study includes pedestrian and bike access
- Planning Board courtesy review in January
- Other
- Met with city representatives from the fire and police departments to share safety plans and get feedback
- The CPT test has been completed, results are expected by the end of the year
Action Items
- Complete PV procurement by Dec 31
- Continue teacher input sessions for design details
- Provide utility cost comparison at next meeting
- Finalize traffic/pedestrian study for Planning Board review
- Prepare for 60% design submission by April 1
Resources
Middle School Project webpage: Middle School Project
This page includes the school building aid application, the full 2022 Preliminary Design Study and documents, reports and presentations by year.
Sign Up for Email Notifications
Updates are sent via the district's ParentSquare app. Share this with anyone that would be interested: Join Community Groups and select "Middle School Project." No phone number is necessary.